Project Network Analysis using CPM and PERT

Notes

Fundamentals of Network Analysis Project management in business requires structured scheduling, coordination, and tracking of interdependent activities. Quantitative network models provide visual and mathematical frameworks to plan complex ventures such as infrastructural expansion, software implementation, and product launches. The two standard methodologies are the Critical Path Method and the Program Evaluation and Review Technique. Critical Path Method Versus PERT The Critical Path Method is deterministic, meaning it assumes that activity durations are known with certainty. It is commonly applied in routine industrial projects like construction. Conversely, the Program Evaluation and Review Technique is probabilistic and suited for research or novel development projects where timeframes are uncertain. PERT utilizes three time estimates for each task: optimistic time, most likely time, and pessimistic time, which are combined into an expected duration using a weighted Beta distribution formula. Calculating Earliest and Latest Times A project network is mapped using nodes and directed arrows representing activities and precedence relationships. A forward pass across the network calculates the Earliest Start time and Earliest Finish time for each activity, moving from start to finish. A backward pass calculates the Latest Finish time and Latest Start time, moving from finish to start. Determining Float and Slack Total float is the length of time an activity can be delayed without extending overall project completion. It is calculated as Latest Start minus Earliest Start, or Latest Finish minus Earliest Finish. Activities with zero total float form the critical path. Any delay along this path directly delays the entire project. Practical example A dairy cooperative in Eldoret is installing a modern milk cooling and pasteurization unit. The project comprises four sequential activities: Activity A: Site clearing and civil foundation works (Duration: 3 weeks; Predecessors: None). Activity B: Equipment procurement and delivery (Duration: 5 weeks; Predecessors: None). Activity C: Machinery installation and electrical wiring (Duration: 4 weeks; Predecessors: Activity A and Activity B). Activity D: Quality inspection and commissioning (Duration: 2 weeks; Predecessors: Activity C). Forward Pass calculations: For Activity A: Earliest Start = 0; Earliest Finish = 0 + 3 = 3 weeks. For Activity B: Earliest Start = 0; Earliest Finish = 0 + 5 = 5 weeks. For Activity C: Must wait for both A and B. Therefore, Earliest Start = maximum(3, 5) = 5 weeks. Earliest Finish = 5 + 4 = 9 weeks. For Activity D: Earliest Start = 9 weeks; Earliest Finish = 9 + 2 = 11 weeks. The minimum project completion duration is 11 weeks. Backward Pass calculations: For Activity D: Latest Finish = 11; Latest Start = 11 - 2 = 9 weeks. Float = 9 - 9 = 0. For Activity C: Latest Finish = 9; Latest Start = 9 - 4 = 5 weeks. Float = 5 - 5 = 0. For Activity B: Latest Finish = 5; Latest Start = 5 - 5 = 0 weeks. Float = 0 - 0 = 0. For Activity A: Latest Finish = 5; Latest Start = 5 - 3 = 2 weeks. Float = 2 - 0 = 2 weeks. The critical path consists of activities with zero float: B -> C -> D, totaling 11 weeks. Activity A has 2 weeks of float.

Quiz

1. What does a total float of 2 weeks for Activity A signify to project managers?

2. In PERT analysis, how is the expected duration of an activity calculated from optimistic (a), most likely (m), and pessimistic (b) estimates?

3. In network analysis, how is the critical path identified?

Sign in to submit and securely grade your quiz.